Kalbert Young, 东精影业 vice president for budget and finance and chief financial officer, provides an update of the legislative session as it heads into its final weeks before the scheduled May 4 adjournment.

The 2023 state legislature is in the final three weeks before its scheduled adjournment on May 4. That means that a number of legislative measures—most notably, the budget—are on their way to the last phase of deliberation this session. The state Senate approved its version of the state budget (HB 300 HD1 SD1) on April 11, and only partially restored funds to 东精影业 to current operating levels for the first year of the biennium. By contrast, the budget passed by the House of Representatives (HB 300 HD1) earlier in the session fully restored funding, as reported in the March 21 legislative update.

Young
Kalbert Young

If the Senate’s version ultimately passes, it would require the university to come back to the Legislature in 2024 to again request restoration of state support to funded operating levels that were in place before the COVID-19 pandemic.

Restoration of public funding levels to the university was the top legislative priority for 东精影业 this legislative session along with expanding the Hawai?i Promise program to the three four-year universities and funding to address healthcare workforce shortages.

The Senate provided no funding to expand Hawai?i Promise and only provided funding for 1 of the 14 requests for additional funding to help address workforce shortages in the healthcare industry.

The General Fund Budget table (at the bottom of the online story) compares the total general fund budgets for the campuses in the 东精影业 Board of Regents, governor, House and Senate versions of the operating budget and the dozens of added items.

The House and the Senate will now begin to negotiate their differences on the budget bills and other measures that are still alive in conference committees. This final process of the session is where selected conferees from each chamber meet behind closed doors to work out differences between their versions of the bills and pass out amended drafts that both chambers agree on. The outcomes of these meetings will ultimately decide funding for 东精影业 and other state agencies.

Capital improvement projects

For the capital improvement projects (CIP) budget, 东精影业 requested $262.5 million for FY24 and $296 million for FY25 in additional General Obligation Bonds to address capital renewal, progress on deferred maintenance and funding for projects to modernize each of the campuses within the 东精影业 System. The plan was for the funds to be equitably and proportionally dispersed.

The Senate’s budget includes $142.5 million for FY24 and $93.7 million for FY25 in General Obligation Bond funding and $91 million for FY24 and $54 million for FY25 in General Funds for various projects.

Upon review and examination of the Senate version of the budget, it appears funds and reductions are disproportionately appropriated in favor of the 东精影业 Community Colleges. 东精影业 was provided a total of $233.5 million in the aggregate. Of that amount, the 东精影业 Community Colleges account for $173.9 million, or 74% of the total amount, even though the seven community colleges make up just 22% of 东精影业’s total gross square footage.

The Senate budget bill provides three individual (yet, repetitive) $35 million appropriations in FY24 for repairing and/or renovating 东精影业 Community College facilities. While 东精影业 Manoa accounts for 67% of the system’s total square footage, the amount appropriated for Renew/Improve/Modernize (RIM) for 东精影业 Manoa, 东精影业 Hilo and 东精影业 West O?ahu campuses, totaled just $17.5 million.

Without at least $50 million per year in RIM funding, 东精影业’s deferred maintenance backlog is estimated to increase to nearly $1 billion in the next few years. Outside of the Community Colleges, 东精影业 currently has at least $80 million of shovel-ready projects that will have to wait another year if funding is not allocated in the final budget.

The CIP budget comparison table (at the bottom of the online story) compares the BOR, governor, House and Senate budgets.

2023 legislative session remaining timeline

The next major deadline will be the final decking of bills on April 28. By this time, all bills must have concluded deliberation in conference committees of both the House and Senate. The Hawai?i State Legislature is scheduled to adjourn on May 4, 2023.

General Fund Budget Table

Campus Description
Board Governor House Senate
FY24 FY25 FY24 FY25 FY24 FY25 FY24 FY25
RESTORATION OF FUNDS
东精影业 惭ā苍辞补 General Fund Restoration $5,600,000 $5,600,000 $5,600,000 $5,600,000 $5,600,000 $5,600,000 $5,600,000
JABSOM General Fund Restoration $1,800,000 $1,800,000 $1,800,000 $1,800,000 $1,800,000 $1,800,000 $1,800,000
东精影业 Hilo General Fund Restoration $3,420,000 $3,420,000 $3,420,000 $3,420,000 $3,420,000 $3,420,000 $3,420,000
东精影业 West O?ahu General Fund Restoration $1,620,000 $1,620,000 $1,620,000 $1,620,000 $1,620,000 $1,620,000 $1,620,000
东精影业 System General Fund Restoration $5,086,848 $5,086,848 $5,086,848 $5,086,848 $5,086,848 $5,086,848 $5,086,848
SUSTAINED FUNDING
东精影业 惭ā苍辞补 Athletics Subsidy Continuation $3,200,000 $3,200,000 $3,200,000 $3,200,000 $3,200,000 $3,200,000 $3,200,000
东精影业 Hilo Athletics Subsidy Continuation $400,000 $400,000 $400,000 $400,000 $400,000 $400,000 $400,000
东精影业 惭ā苍辞补 HIMB Full Year Funding $85,500 $85,500 $85,500 $85,500 $85,500 $85,500 $85,500 $85,500
JABSOM GME Residency Full Year Funding $1,670,000 $1,670,000 $660,000 $660,000 $660,000 $660,000 $660,000 $660,000
JABSOM Neighbor Island MD Expansion Continuation $2,000,000 $2,000,000 $2,000,000 $2,000,000 $2,000,000 $2,000,000 $2,000,000
HAWAI?I PROMISE PROGRAM
东精影业 惭ā苍辞补 Hawai?i Promise Expansion $12,300,000 $12,300,000 $12,300,000 $12,300,000 $12,300,000 $12,300,000
东精影业 Hilo Hawai?i Promise Expansion $1,700,000 $1,700,000 $1,700,000 $1,700,000 $1,700,000 $1,700,000
东精影业 West O?ahu Hawai?i Promise Expansion $5,000,000 $5,000,000 $5,000,000 $5,000,000 $5,000,000 $5,000,000
东精影业 Community Colleges Hawai?i Promise Continuation $3,700,000 $3,700,000 $3,700,000 $3,700,000 $3,700,000 $3,700,000 $3,700,000
CAMPUS FACILITIES AND CORE SERVICES
东精影业 Hilo Security Officers $313,320 $313,320
东精影业 West O?ahu Security Officers $30,900 $61,800
东精影业 Community Colleges Security Officers $693,780 $1,456,938 $693,780 $1,456,938 $1 $1 $693,780 $1,456,938
东精影业 Hilo IT Support $160,000 $160,000
东精影业 Hilo Analytical Lab Manager $80,000 $80,000
东精影业 West O?ahu Campus and ACM Support $162,996 $325,992
EARLY COLLEGE EXPANSION
东精影业 Community Colleges Early College Expansion $577,500 $1,212,750
东精影业 West O?ahu Early College Expansion $90,000 $180,000
东精影业 Hilo Early College Expansion $90,000 $180,000
INITIATIVE: SUPPORT STUDENT SUCCESS
东精影业 West O?ahu Student Success Support $261,252 $522,504
东精影业 Community Colleges 东精影业 Maui College—Health Center $98,500 $200,250 $98,500 200,250 $98,500 200,250 $98,500 200,250
东精影业 Community Colleges 东精影业 Maui College-Distance Learning $73,500 $147,750
东精影业 惭ā苍辞补 Kūlia I Ka Nu?u Undergraduate Research Initiative $721,600 $1,058,400
东精影业 Hilo Transfer Center $60,000 $60,000
东精影业 Hilo Career Advising and Internship Admin $60,000 $60,000
东精影业 Community Colleges Windward CC—Incarcerated Students $125,500 $241,550
东精影业 Community Colleges Hawai?i CC—Incarcerated Students $37,500 $78,750
ADDRESS AREAS OF STATE NEED
东精影业 Hilo Administration of Justice Program Expansion $142,000 $142,000
东精影业 Hilo MA Teaching Expansion and Kahuawaiola Indigenous Teacher Education $210,000 $210,000
东精影业 Hilo MA Counseling Psychology $210,000 $210,000
东精影业 Hilo CAFNRM Sustainable Agribusiness $100,000 $100,000
东精影业 West O?ahu Teacher Preparation $70,676 $141,352
INDUSTRY INITIATIVE: HEALTH
东精影业 West O?ahu Health and Wellness $147,158 $294,316 $147,158 $294,316 $147,158 $294,316
东精影业 惭ā苍辞补 Health Science Initiative $477,009 $688,473 $477,009 $688,473 $477,009 $688,473
东精影业 Community Colleges Kapi?olani CC—Allied Health Professions and NI Expansion $761,000 $761,000 $761,000 $761,000 $761,000 $761,000
东精影业 Community Colleges Windward CCCNA Program Support $86,000 $86,000 $86,000 $86,000
东精影业 Community Colleges Kaua?i CC—Medical Assisting Program Support $232,000 $232,000 $232,000 $232,000 $232,000 $232,000
东精影业 Community Colleges Kapi?olani CC—Nursing Clinical Faculty $259,998 $259,998 $259,998 $259,998 $259,998 $259,998
东精影业 Community Colleges Hawai?i CC—Nursing Program Maintenance and Expansion $474,000 $474,000 $474,000 $474,000 $474,000 $474,000
东精影业 Community Colleges Kaua?i CC—Nursing Faculty $258,000 $258,000 $258,000 $258,000
东精影业 Community Colleges 东精影业 Maui College—Nursing Faculty $172,000 $172,000 $172,000 $172,000 $172,000 $172,000
东精影业 Community Colleges 东精影业 Maui College—CNA to LPN Program Support $86,000 $86,000 $86,000 $86,000 $86,000 $86,000
东精影业 惭ā苍辞补 东精影业 West O?ahu东精影业 惭ā苍辞补 Nursing Collaboration $503,000 $503,000 $503,000 $503,000
东精影业 惭ā苍辞补 NAWSON Programs and Training Support $661,430 $661,430 $661,430 $661,430 $661,430 $661,430
东精影业 Hilo Nursing Faculty Support $198,000 $198,000 $198,000 $198,000
东精影业 惭ā苍辞补 Adjust 东精影业 West O?ahu东精影业 惭ā苍辞补 NAWSON Collaboration Request $423,000 $1
东精影业 Hilo Adjust 东精影业 Hilo School of Nursing Request $430,306 $461,717 $1 $1
东精影业 惭ā苍辞补 Thompson School of Social Work and Public Health-Training Hubs $457,000 $457,000 $1 $1 $228,500 $457,000
东精影业 惭ā苍辞补 东精影业 West O?ahu东精影业 惭ā苍辞补 NAWSON Collaboration Request $628,306 $659,717 $1 $1
东精影业 Hilo 东精影业 Hilo Nursing Faculty $503,000 $926,000 $1 $1
GOVERNOR’S ADD-ONS
东精影业 惭ā苍辞补 Restore Funds for Previously Unfunded Positions $6,073,157 $6,073,157
JABSOM Restore Funds for Previously Unfunded Positions $926,843 $926,843
东精影业 Cancer Center Restore Funds for Previously Unfunded Positions $1,000,000 $1,000,000
东精影业 Hilo Restore Funds for Previously Unfunded Positions $1,000,000 $1,000,000
东精影业 West O?ahu Restore Funds for Previously Unfunded Positions $1,000,000 $1,000,000
HOUSE ADD-ONS
东精影业 Community Colleges Office of International and Regional Partnerships Study Abroad Program $15,000
东精影业 Community Colleges Placeholder Amounts for Transfers $12 $12
东精影业 System IT Equipment $75,000 $75,000
SENATE ADD-ONS
东精影业 惭ā苍辞补 CIP—Waikīkī Aquarium Seawall Repair $3,000,000
东精影业 惭ā苍辞补 Water Resources Research Center—Wastewater Demo Pilot Program $3,025,468
东精影业 Community Colleges Repairs and Maintenance and Deferred Maintenance $35,000,000
东精影业 Community Colleges Non-Credit Workforce Development $578,240 $578,240
东精影业 Community Colleges Campus Coordinators and Counselors (Early College) $577,500 $1,212,750
? Total $56,266,967 $59,399,921 $63,698,835 $65,831,187 $50,031,460 $50,476,833 $70,774,336 $4,650,678

CIP Budget Table

Campus Description MOF
Board of Regents Executive Request House Senate
FY24 FY245 FY24 FY245 FY24 FY245 FY24 FY245
东精影业 System Renew, Improve and Modernize C $100,000,000 $100,000,000 $20,000,000 $20,000,000 $20,000,000 $20,000,000 $1,000 $1,000
东精影业 System Renew, Improve and Modernize A $30,000,000 $30,000,000 $30,000,000 $30,000,000 $11,000,000 $22,500,000
东精影业 Hilo Renew, Improve and Modernize C $17,500,000 $26,500,000 $17,500,000 $26,500,000 $10,000,000 $26,500,000 $6,500,000 $24,000,000
东精影业 Community Colleges Renew, Improve and Modernize C $25,000,000 $25,000,000
东精影业 Community Colleges Renew, Improve and Modernize A $25,000,000 $25,000,000 $25,000,000 $25,000,000 $60,000,000 $25,000,000
东精影业 West O?ahu Renew, Improve and Modernize C $5,000,000 $3,500,000 $5,000,000 $3,500,000 $1,000 $1,000
东精影业 惭ā苍辞补 PV Rooftop and Canopies and various Energy Efficiency Projects C $20,000,000 $20,000,000 $20,000,000 $20,000,000 $20,000,000
东精影业 Community Colleges Minor CIP C $25,000,000 $25,000,000
东精影业 Community Colleges Minor CIP A $20,000,000 $20,000,000 $20,000,000 $20,000,000 $25,000,000 $25,000,000
东精影业 惭ā苍辞补 Assessment and Feasibility of Hamilton Library C $6,500,000
东精影业 West O?ahu Road B Entry Plaza C $5,500,000 $5,500,000 $1,000
东精影业 Community Colleges Kapi?olani CC-Replace AC System (6930 Ohelo) C $15,000,000 $15,000,000 $15,000,000
东精影业 Community Colleges Kapi?olani CC-Upgrade Fire Alarm System C $8,500,000 $8,500,000 $8,500,000
东精影业 惭ā苍辞补 Mini Master Plan Phase 3-Kuykendall Hall C $5,000,000
东精影业 West O?ahu Campus Center Phase II C $49,000,000
东精影业 Community Colleges Windward CC-Repair/Replace HVAC (5988 ?Imiloa) C $11,000,000 $11,000,000 $11,000,000 $5,500,000
东精影业 惭ā苍辞补 Athletics C $12,000,000 $18,000,000 $1,000 $1,400,000
东精影业 惭ā苍辞补 Athletics A $4,500,000
东精影业 Community Colleges Kapi?olani CC-Renovate Building (6920 Koki?o) C $2,000,000 $10,000,000 $2,000,000 $10,000,000 $10,000,000 $2,000,000 $10,000,000
东精影业 惭ā苍辞补 Administrative Office and Parking C $8,000,000
东精影业 Community Colleges Honolulu CC-Technology Renovations Phase 2 C $3,000,000 $3,000,000 $3,000,000
东精影业 惭ā苍辞补 Holmes Hall C $1,500,000 $6,000,000 $1,500,000 $6,000,000 $6,000,000 $1,500,000
东精影业 Community Colleges Hawai?i CC-Manono Campus Development C $2,000,000 $2,000,000 $2,000,000
东精影业 惭ā苍辞补 Waikīkī Aquarium Seawall Repair C $3,000,000 $3,000,000 $3,000,000
东精影业 惭ā苍辞补 HIMB-Continue DARPA Prototype Artificial Reef C $50,000,000 $50,000,000 $25,000,000
东精影业 惭ā苍辞补 HIMB-Replacement of Sewage System, Seawall and Pier C $10,000,000
东精影业 Community Colleges 东精影业 Maui-Renovate Existing Buildings for Medical Education Classrooms C $250,000
东精影业 Community Colleges Waiākea Research Station C $1,000 $2,625,000
东精影业 System Waiale?e Ag Substation Improvements A $4,000,000
东精影业 Hilo Library A/C Improvements A $1,500,000 $8,000,000
东精影业 Hilo RIM College Hall C Renovations A $1,200,000
东精影业 Hilo RIM Portables 1-4 A $2,500,000
东精影业 Hilo RIM Portables 5-7 A $3,000,000
东精影业 Hilo Science Technology Building A/C Improvements A $1,000,000
东精影业 Hilo University Classroom Building Renovations A $500,000 $4,500,000
东精影业 Community Colleges Kaua?i CCPV Rooftops/Canopies C $15,000,000
东精影业 Community Colleges Kaua?i CC-Student Dorms and Faculty/Staff Housing A $250,000
东精影业 Community Colleges Various Repairs and Deferred Maintenance A $35,000,000
东精影业 System Coconut Island Sewer Line Replacement/Upgrades A $750,000 $5,000,000
? Total $262,500,000 $296,000,000 $189,000,000 $161,000,000 $180,252,000 $187,500,000 $233,528,000 $147,702,000

MOF A = General Funds, MOF C = GO Bonds